Sunday, September 11, 2011

Summer Landscape Mini-Term Recap

What a summer! Even though it was a HOT, muddy, dirty process the time spent building the New Norris House landscape is one that I will always remember fondly. I even miss the manual labor, but maybe that's because I'm in an air conditioned room right now...

During the landscape mini-term we accomplished so much. We finished building and installed plants on the terraced bioretention beds.

We excavated for, and built, the raised vegetable beds and installed the 200 gallon irrigation cistern.


We successfully installed the stormwater overflow from the irrigation cistern to the bioretention beds and installed the pipe that brings the house's greywater into the greywater bioretention bed. We also built a gravel plinth for forest-side seating, installed over 200 linear feet of aluminum bed edging, dug beds for the perennial plantings, worked with a local contractor to finish the site grading, installed a stepping stone path connecting the sidewalk to the existing walking trails behind our property, weeded, watered and installed erosion control measures.


Some of us even got a lesson in how to operate landscape machinery!


So far, the plants are doing fantastic. The bioretention beds are lush and the perennial beds are off to a great start. We have plans for native shrub and tree planting in the fall, but for now it is so nice to be able to see what started as just an idea on paper growing and thriving in reality. Thank you to everyone who helped make the mini-term such a huge success!

Friday, September 17, 2010

Excavation Begins




Excavation of the site began yesterday. This is such a big step not only because it signifies our on-site construction is underway but also because it commences our LEED efforts to keep the site sustainable. The orange band seen in the pictures is the silt barrier which has been installed to keep the top soil from leaving the site. As simple as it seems, this band is very important for keeping erosion to a minimum as construction progresses. We were happy to receive an email from Bruce, our LEED Green Rater from NRG, saying our efforts were looking good so far!